KHUJAND, June 28, 2011, Asia-Plus -- Installation of the second transformer at the Sughd-500 substation in Ghonchi district has improved electricity supplies in northern Tajikistan, Mumin Toshmatov, the deputy head of Barqi Tojik’s branch in Sughd, says.
An official introduction of the second transformer into operation took place on June 26. The northern Sughd province now receives more than 13 million kWh of electricity per day. Before that, when only one transformer with capacity of only 10 million kWh of electrical power per day operated, the province was receiving just little more than 12 million kWh of electricity per day.
Installation of the second transformer has increased the substation capacity to 27 million kWh of electricity per day, Toshmatov added.
According to specialists from Barqi Tojik, current Sughd’s daily requirements in electricity are up to 14 million kWh.





The tragedy in Mina: the crime that could end Donald Trump and his Defense Secretary's careers
The bilateral trade between Uzbekistan and Tajikistan could grow another 40%, expert says
Representative of Tajikistan discusses the Role of Eurasian Transport Routes at Global Forum in Baku
Financial literacy key to survival for rural Tajik families
U.S. State Department offers $10 million reward for Information on Iran’s new Supreme Leader
The ASAN model - one of the central pillars of Azerbaijan’s national anticorruption strategy
This week in Tajikistan saw a series of notable developments
Celebrations for Navrouz in Dushanbe: a grand festival at Navrouzgoh complex
Russia's power sector in Central Asia faces growing challenges amid financial strain
Military court in St. Petersburg jails Tajik citizen for justifying terrorist attack at Crocus City Hall
All news
Авторизуйтесь, пожалуйста